  1. PERT technique of network analysis is mainly useful for

  2. A.

     Small projects

    B.

     Large and complex projects

    C.

     Research and development projects

    D.

     Deterministic activities


  3. In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?

  4. A.

     Yes, because of heavier overheads and handling cost

    B.

     Yes, because of the very high order of quality control for the factory made components

    C.

     No, because of repetitive manufacture of a number of elements

    D.

     No, because of savings in site labour


  5. What estimate would you give for the variance in above problem ?

  6. A.

     81

    B.

     54

    C.

     36

    D.

     9


  7. Mobilization advance up to 10% of the cost of work is given to a contractor

  8. A.

     On commencement of work at site for payment of loan taken by him

    B.

     For the purchase of construction materials

    C.

     For the payment of advances to labour and other staff

    D.

     For all activities required to start the work at site on finalization of the contract document


  9. Which of the following is not a PERT event?

  10. A.

     Site investigation started

    B.

     Sessional work completed

    C.

     Bus starts from Jaipur

    D.

     Class is being attended


  11. During the construction period, price variation clause in contracts caters to

  12. A.

     Increase in rates of only important materials

    B.

     Variation in cost in materials element, labour element and petrol-oil-lubricant element

    C.

     Variation in total cost of the project on an ad hoc basis

    D.

     Rate of inflation


  13. In PERT analysis, the time estimates of activities and probability of their occurrence follow

  14. A.

     Normal distribution curve

    B.

     Poisson's distribution curve

    C.

     Beta distribution curve

    D.

     None of the above


  15. At a work site, statistical quality control of concrete means

  16. A.

     Measurement of risks to eliminate failures

    B.

     Applying the theory' of probability to sample testing or inspection

    C.

     Reduction in wastage of inspection costs

    D.

     Reduction in costs for the removal of defects


  17. Pick up the incorrect statement from the following:

  18. A.

     An activity of a project is denoted by an arrow on the net work

    B.

     The tail of the arrow indicates the start of the activity

    C.

     The head of the arrow indicates the end of the activity

    D.

     The arrows are drawn to scale from left to right


  19. Pick up the PERT event from the following:

  20. A.

     Digging of foundation started

    B.

     Digging of foundation completed

    C.

     Laying of concrete started

    D.

     All the above