- During the construction period, price variation clause in contracts caters to
|
A.
Increase in rates of only important materials |
|
B.
Variation in cost in materials element, labour element and petrol-oil-lubricant element |
|
C.
Variation in total cost of the project on an ad hoc basis |
|
D.
Rate of inflation |
Answer : Option B
Explanation :
Explanation Not Provided