  1. In PERT analysis, the time estimates of activities and probability of their occurrence follow

  2. A.

     Normal distribution curve

    B.

     Poisson's distribution curve

    C.

     Beta distribution curve

    D.

     None of the above

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    Explanation Not Provided