Civil Engineering :: Construction Planning and Mgmt
- The most popular type of organization used for Civil Engineering Constructions, is
- CPM is
- In time-cost optimization of a project, crashing is done.
- Earliest finish of an activity is always
- Latest start of an activity is always
- The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively
- In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
- A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be
-
Consider the following statements for a power shovel:
(i) Output can be increased by reducing the angle of swing for a given depth of cut.
(ii) For a given angle of swing, output will be maximum at optimum depth of cut.
(iii) Output can be increased by keeping the depth of cut less than optimum depth.
(iv) Output can be increased by increasing the size of shovel.