- For which of the following materials, the output of power shovels for a fixed shovel size will be maximum
- The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be
- Crash project duration is obtained by summing the
- Which one of the following represents an activity?
-
The part of a derrick crane include
(i) Mast
(ii) Boom
(iii) Bull wheel
(iv) Jack
which of these statements are correct? - For excavating utility trenches with precise control of depth, the excavation equipment used is
- Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?
- Power stations are generally treated as
- If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then
A.
Normal durations for all the activities |
B.
Crash durations for all activities |
C.
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities |
D.
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities |