Civil Engineering :: Construction Planning and Mgmt
- While scheduling a project by C.P.M.
- Final technical authority of a project lies with
- The technique for establishing and maintaining priorities among the various jobs of a project, is known
- If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
-
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
-
The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
- Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
- Which one of the following represents an event?
- The reduction in project time normally results in
-
In the given figure, the network of a project represents