- Pick up the incorrect statement from the following:
A.
An activity of a project is denoted by an arrow on the net work |
B.
The tail of the arrow indicates the start of the activity |
C.
The head of the arrow indicates the end of the activity |
D.
The arrows are drawn to scale from left to right |
Answer : Option D
Explanation :
Explanation Not Provided