- In time-cost optimization of a project, crashing is done.
A.
On all the activities |
B.
On all the activities lying on the critical path |
C.
Only on activities lying on the original critical path and having flatter cost slopes |
D.
On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope |
Answer : Option D