  1. In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having

  2. A.

     Longest duration

    B.

     Highest cost slope

    C.

     Least cost slope

    D.

     Shortest duration

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    Explanation Not Provided