- Latest start of an activity is always
A.
greater than or equal to latest event time of preceding node |
B.
less than or equal to latest event time of preceding node |
C.
equal to latest event time of preceding node |
D.
less than latest event time of preceding node |
Answer : Option A
Explanation :
Explanation Not Provided