- Latest start of an activity is always
|
A.
greater than or equal to latest event time of preceding node |
|
B.
less than or equal to latest event time of preceding node |
|
C.
equal to latest event time of preceding node |
|
D.
less than latest event time of preceding node |
Answer : Option A
Explanation :
Explanation Not Provided