- Earliest finish of an activity is always
A.
Greater than earliest event time of the following node |
B.
Less than earliest event time of the following node |
C.
Less than or equal to earliest event time of the following node |
D.
Greater than or equal to earliest event time of the following node |
Answer : Option C
Explanation :
Explanation Not Provided