Discussion :: Construction Planning and Mgmt
- Crash project duration is obtained by summing the
|
A.
Normal durations for all the activities |
|
B.
Crash durations for all activities |
|
C.
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities |
|
D.
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities |
Answer : Option D
Explanation :
Explanation Not Provided
Be The First To Comment

Whatsapp
Facebook