  1. If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

  2. A.

     expected time of activity A is greater than the expected time of activity B

    B.

     expected time of activity B is greater than the expected time of activity A

    C.

     expected time of both activities A and B are same

    D.

     none of the above

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    Explanation Not Provided