- If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then
A.
expected time of activity A is greater than the expected time of activity B |
B.
expected time of activity B is greater than the expected time of activity A |
C.
expected time of both activities A and B are same |
D.
none of the above |
Answer : Option C
Explanation :
Explanation Not Provided