  1. The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is

  2. A.

     19

    B.

     14

    C.

     24

    D.

     None of these

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    Explanation Not Provided