  1. Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

  2. A.

     20

    B.

     25

    C.

     35

    D.

     15

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    Explanation Not Provided