Civil Engineering :: Construction Management
-
While scheduling a project by C.P.M.
-
If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is
-
Pick up the correct statement from the following:
-
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
-
For the execution of a project, a contractor is
-
Railway projects are treated as
-
Pick up the correct statement from the following:
-
The main disadvantage of line organisation, is
-
Pick up the correct statement from the following: