Discussion :: Construction Management
-
Pick up the correct statement from the following:
A.
Earliest expected time is denoted by TE |
|
B.
|
|
C.
Contractual obligation time is denoted by Ts |
|
D.
Latest occurrence time is taken as contractual obligation time |
|
E.
All the above. |
Answer : Option E
Explanation :
No answer description available for this question.