  1. Pick up the correct statement from the following:

  2. A.

    The difference of latest occurence time and earliest expected time, is called slack

    B.

    The activities connecting the events having zero slack, lie on the critical path

    C.

    The critical path consumes the maximum time

    D.

    All the above.

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    No answer description available for this question.