  1. Frequency distribution curves

  2. A.

    having a single lump, are called uninodal curves

    B.

    if symmetrical, are called normal curves

    C.

    if not symmetrical, are called skew curves

    D.

    all the above.


  3. Pick up the correct statement from the following:

  4. A.

    Programme Evaluation and Review Technique, is event oriented

    B.

    Programme Evaluation and Review Technique is not event oriented

    C.

    Critical Path Method is event oriented

    D.

    Critical Path method is event oriented.


  5. The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is

  6. A.

    19

    B.

    14

    C.

    24

    D.

    None of these.


  7. Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

  8. A.

    20

    B.

    25

    C.

    35

    D.

    15


  9. While filling the tender for any work, the contractor considers

  10. A.

    site survey

    B.

    availability of construction materials

    C.
    availability of labour
    D.

    study of specifications

    E.

    all the above.