Home / Mechanical Engineering / Industrial Engineering and Prod'n Mgmt :: section-1

Mechanical Engineering :: Industrial Engineering and Prod'n Mgmt

  1. One time measurement unit (TMU) in method time measurement system equals

  2. A.

     0.0001 minute

    B.

     0.0006 minute

    C.

     0.006 minute

    D.

     0.001 minute


  3. The main object of scientific layout is

  4. A.

     To produce better quality of product

    B.

     To utilize maximum floor area

    C.

     To minimize production delays

    D.

     All of these


  5. The most important function of inventory control is

  6. A.

     Stock control system

    B.

     To run the stores effectively

    C.

     Technical responsibility for the state of materials

    D.

     All of the above


  7. The average time recorded by work study man for an operation is called

  8. A.

     Standard time

    B.

     Normal time

    C.

     Representative time

    D.

     None of these


  9. Merit Rating is the method of determining worth of

  10. A.

     A job

    B.

     An individual employee

    C.

     A particular division in workshop

    D.

     Machine


  11. Which one of the following techniques is used for determining allowances in time study?

  12. A.

     Acceptance sampling

    B.

     Linear regression

    C.

     Performance rating

    D.

     Work sampling


  13. The critical path of a network represents

  14. A.

     The minimum time required for completion of project

    B.

     The maximum time required for completion of project

    C.

     Maximum cost required for completion of project

    D.

     Minimum cost required for completion of project


  15. Job evaluation is the method of determining the

  16. A.

     Relative worth of jobs

    B.

     Skills required by a worker

    C.

     Contribution of a worker

    D.

     Contribution of a job


  17. Merit rating is the method of determining the

  18. A.

     Relative values of a job

    B.

     Workers performance on a job

    C.

     Worth of a machine

    D.

     Value of overall production


  19. Which of the following is independent of sales forecast?

  20. A.

     Productivity

    B.

     Inventory control

    C.

     Production planning

    D.

     Production control