Discussion :: Industrial Engineering and Prod'n Mgmt
- The critical path of a network represents
|
A.
The minimum time required for completion of project |
|
B.
The maximum time required for completion of project |
|
C.
Maximum cost required for completion of project |
|
D.
Minimum cost required for completion of project |
Answer : Option A
Explanation :
The critical path of a network represents The minimum time required for completion of project
Be The First To Comment

Whatsapp
Facebook