Home / Civil Engineering / Estimating and Costing :: section-3

Civil Engineering :: Estimating and Costing

  1. If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is

  2. A.

     30 D

    B.

     39 D

    C.

     50 D

    D.

     59 D


  3. The most reliable estimate is

  4. A.

     Detailed estimate

    B.

     Preliminary estimate

    C.

     Plinth area estimate

    D.

     Cube rate estimate


  5. The main factor to be considered while preparing a detailed estimate, is

  6. A.

     Quantity of the materials

    B.

     Availability of materials

    C.

     Transportation of materials

    D.

     All the above


  7. The order of booking dimensions is

  8. A.

     Length, breadth, height

    B.

     Breadth, length, height

    C.

     Height, breadth, length

    D.

     None of these


  9. The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is

  10. A.

     (6 + 15) chains

    B.

     (6 + 12) chains

    C.

     (6 + 18) chains

    D.

     None of these


  11. The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is

  12. A.

     1.00 m³

    B.

     1.25 m³

    C.

     1.50 m³

    D.

     1.75 m³


  13. Pick up the correct statement regarding the centre line method of estimating a building

  14. A.

     Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item

    B.

     The centre line is worked out separately for different sections of walls of a building

    C.

     The centre line length is reduced by half the layer of main wall joining the partition wall

    D.

     All the above


  15. For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is

  16. A.

     0.200 m³

    B.

     0.247 m³

    C.

     0.274 m³

    D.

     0.295 m³


  17. For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is

  18. A.

     0.90 m³

    B.

     0.94 m³

    C.

     0.98 m³

    D.

     1.00 m³


  19. The measurement is not made in square meters in case of

  20. A.

     D.P.C. (Damp proof course)

    B.

     Form works

    C.

     Concrete Jeffries

    D.

     R.C. Chhajja