CSE MCQs :: Agile Testing

  1. When is Acceptance Testing performed in Agile development?
  2. A.
    On request of customer
    B.
    After system is ready
    C.
    At the end of each iteration
    D.
    Daily

  3. What is NOT a characteristic of a good user story?
  4. A.
    Value
    B.
    Negotiable
    C.
    Estimateable
    D.
    Dependant

  5. If a team can complete 10 story points In an iteration then how long will it take for the team to complete 100 story points?
  6. A.
    10 Iterations
    B.
    10 waves
    C.
    20 Iterations
    D.
    20 waves

  7. Agile is
  8. A.
    Sequential
    B.
    Iterative
    C.
    Incremental
    D.
    Both B & C

  9. When acceptance testing is performed in Agile development?
  10. A.
    On request of customer
    B.
    After system is ready
    C.
    At the end of each iteration
    D.
    Daily

  11. Which of the following is NOT one of the five core risk areas common to all projects?
  12. A.
    Specification Breakdown
    B.
    Scope Creep
    C.
    Strategic Alienation
    D.
    Intrinsic Schedule Flaw

  13. Find what is the unit of measurement that is used to measure the size of a user story for an Agile project?
  14. A.
    Function points
    B.
    Story points
    C.
    Work breakdown points
    D.
    Velocity points

  15. This is one of the estimation technique.It involves splitting a story or feature into smaller, easier-to-estimate pieces.
  16. A.
    Disaggregation
    B.
    Triangulation
    C.
    Planning Poker
    D.
    Velocity Driven estimation

  17. Which of the following is the BEST approach for estimation?
  18. A.
    Expert opinion
    B.
    Analogy
    C.
    Disaggregation
    D.
    A combination of all of the above