- Rotary drilling
-
For providing a raft foundation, the following activities are involved
1.Ramming the foundation bed
2.Excavation of the soil upto required depth
3.Laying the reinforcement over the foundation bed
4.Curing the cement concrete placed over reinforcement
5.Pouring the cement concrete over the reinforcement
The correct sequence is - Queen closer may be placed
- The differential settlement in case of foundations on sandy soils should not exceed
- The width of the hollow space between two walls of a cavity wall should not exceed
- For a rectangular foundation of width b, eccentricity of load should not exceed
- The vertical member running through middle of a shutter frame, is
- Slate
- The members which support covering material of a sloping roof, are
-
Assertion A : Shishum is used for decorative woodwork.
Reason R : Shishum can be polished to an excellent finish.