Home / Civil Engineering / Building Construction :: Discussion

Discussion :: Building Construction

  1. For providing a raft foundation, the following activities are involved
    1.Ramming the foundation bed
    2.Excavation of the soil upto required depth
    3.Laying the reinforcement over the foundation bed
    4.Curing the cement concrete placed over reinforcement
    5.Pouring the cement concrete over the reinforcement
    The correct sequence is

  2. A.

     1, 2, 3, 4, 5

    B.

     5, 4, 3, 2, 1

    C.

     2, 1, 3, 5, 4

    D.

     3, 2, 5, 1, 4

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    Explanation Not Provided


Be The First To Comment