Home / Arithmetic Aptitude / Time and Work :: General Questions -2

Arithmetic Aptitude :: Time and Work

  1. A and B can do a piece of work in 7 days. With the help of C they finish the work in 5 days. C alone can do that piece of work in?
  2. A.
    1 day
    B.
    10 days
    C.
    30 days
    D.
    32 days

  3. Ravi can do a piece of work in 30 days while Prakash can do it in 40 days. In how many days will they finish it together?
  4. A.
    17 1/7 days
    B.
    27 1/7 days
    C.
    23 2/7 days
    D.
    16 4/11 days

  5. Anil can do a work in 15 days while Sunil can do it in 25 days. How long will they take if both work together?
  6. A.
    3 4/9 days
    B.
    8 4/9 days
    C.
    9 3/8 days
    D.
    6 3/8 days

  7. A can do a job in 18 days and B can do it in 30 days. A and B working together will finish twice the amount of work in ------- days?
  8. A.
    21 ½ days
    B.
    22 ½ days
    C.
    23 ½ days
    D.
    12 ½ days

  9. A can do a piece of work in 10 days and B can do it in 15 days and C can do it 20 days. They started the work together and A leaves after 2 days and B leaves after 4 days from the beginning. How long will work lost?
  10. A.
    8 2/3 days
    B.
    9 2/3 days
    C.
    10 2/3 days
    D.
    10 days

  11. A can do a piece of work in 12 days. When he had worked for 2 days B joins him. If the complete work was finished in 8 days. In how many days B alone can finish the work?
  12. A.
    18 days
    B.
    12 days
    C.
    24 days
    D.
    10 days

  13. A and B together can do a work in 6 days. If A alone can do it in 15 days. In how many days can B alone do it?
  14. A.
    10
    B.
    15
    C.
    12
    D.
    16

  15. A can do a piece of work in 15 days and B in 20 days. They began the work together but 5 days before the completion of the work, A leaves. The work was completed in?
  16. A.
    8 days
    B.
    10 days
    C.
    15 days
    D.
    11 3/7 days

  17. A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start the work together but C leaves 4 days before the completion of the work. In how many days is the work done?
  18. A.
    15 days
    B.
    14 days
    C.
    13 days
    D.
    11 days

  19. A is thrice as efficient as B and is, therefore, able to finish a piece of work 10 days earlier than B. In how many days A and B will finish it together?
  20. A.
    3 1/2 days
    B.
    3 4/5 days
    C.
    3 days
    D.
    5 days