Arithmetic Aptitude :: Time and Work
1. Work from Days:
If A can do a piece of work in n days, then A's 1 day's work = \( \frac { 1 } { n }\)
2. Days from Work:
If A's 1 day's work = \( \frac { 1 } { n }\) , then A can finish the work in n days.
3. Ratio :
If A is thrice as good a workman as B, then:
Ratio of work done by A and B = 3 : 1.
Ratio of times taken by A and B to finish a work = 1 : 3.