  1. A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

  2. A.
    0.50
    B.
    0.66
    C.
    0.84
    D.
    0.95

    View Answer

    Workspace

    Answer : Option C

    Explanation :