  1. The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as

  2. A.

     Duration

    B.

     Total float

    C.

     Free float

    D.

     Interfering float

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    Free Float is the amount of time that an activity can be delayed without delaying the early start date of any successor activity.