  1. Positive slack on a PERT indicates that project is

  2. A.

     Ahead of schedule

    B.

     Beyond schedule

    C.

     As per schedule

    D.

     On critical path

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    A positive slack indicates the amount of time that the task can be delayed without delaying the project finish date.