  1. In Halsey 50-50 plan, output standards are established

  2. A.

     By time study

    B.

     From previous production records

    C.

     From one's judgment

    D.

     All of the above

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    In Halsey 50-50 plan, output standards are established From previous production records