- In crash program for a project
|
A.
both direct and indirect costs, increase |
|
B.
indirect costs increase and direct costs decrease |
|
C.
direct costs increase and indirect costs decrease |
|
D.
cost is no criterion |
Answer : Option C
Explanation :
In crash program for a project direct costs increase and indirect costs decrease