- Which of the following statement is correct?
|
A.
When slack of an activity is zero, it falls only on critical path. |
|
B.
CPM technique is useful to minimize the direct and indirect expenses. |
|
C.
Critical path of a net work represents the minimum time required for completion of project. |
|
D.
All of the above |
Answer : Option D
Explanation :
-When slack of an activity is zero, it falls only on critical path.
- CPM technique is useful to minimize the direct and indirect expenses.
- Critical path of a net work represents the minimum time required for completion of project.