Home / Mechanical Engineering / Industrial Engineering and Prod'n Mgmt :: Discussion

Discussion :: Industrial Engineering and Prod'n Mgmt

  1. CPM is the

  2. A.

     Time oriented technique

    B.

     Event oriented technique

    C.

     Activity oriented technique

    D.

     Target oriented technique

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    CPM is the Activity oriented technique


Be The First To Comment