Discussion :: IBPS BANK EXAM TEST 2
-
4 women and 12 children together take 4 days to complete a piece of work. How many days will 4 children alone take to complete the piece of work if 2 women alone can complete the piece of work in 16days?
Answer : Option B
Explanation :
2 women complete the work in 16 days
∴ 4 women complete the same work in 8 days
∴ Work done by 4 women in 4 days = 1/2
∴ 12 children complete the work in 8 days.
∴ 4 children complete the work in = 3 * 8 = 24 days