Discussion :: GATE Production
-
A firm produces 120 units of product in every 8 hour shift. Four operations as given below are needed to manufacture each unit of product.The above operations are to be assigned to workstations, such that one or more operations are performed in each workstation. Only one unit of product will be processed in each workstation at a time. The minimum number of workstations that will achieve the production target, without violating the precedence constraints, is
Answer : Option C
Explanation :
-NA-
Be The First To Comment