Discussion :: GATE Production
-
Consider a two machine flow shop where jobs are first processed in Machine X and then in Machine Y, in the same sequence. The processing times of four jobs (1, 2, 3 and 4) on the machines are:The sequence of jobs on the machines that minimizes make span is
Answer : Option A
Explanation :
-NA-
Be The First To Comment