  1. Data for four jobs that need to be processed on a single machine are given below.
    Job                                     P  Q   R    S
    Processing time (days)  12 9   21 10
    Due date (days)              20 40 30 19
    All the four jobs are available at time zero. If the jobs are scheduled using the Earliest Due Date (EDD) algorithm, then the job with maximum tardiness is
  2. A.
    P
    B.
    Q
    C.
    R
    D.
    S

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    -NA-