Home / GATE 2017-2018 / GATE Production :: Discussion

Discussion :: GATE Production

  1. Which one of the following is NOT a decision taken during the aggregate production planning stage?
  2. A.
    Scheduling of machines
    B.
    Amount of labour to be committed
    C.
    Rate at which production should happen
    D.
    Inventory to be carried forward

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    -NA-


Be The First To Comment