For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.If the duration of activity f alone is changed from 9 to 10 days, then the
A.
critical path remains the same and the total duration to complete the project changes to 19 days.
|
B.
critical path and the total duration to complete the project remain the same.
|
C.
critical path changes but the total duration to complete the project remains the same.
|
D.
critical path changes and the total duration to complete the project changes to 17 days.
|
Answer : Option A
Explanation :
-NA-