Home / eLitmus Sample Papers with Answers / eLitmus Aptitude Test Paper :: Discussion

Discussion :: eLitmus Aptitude Test Paper

  1. A can complete a piece of work in 4 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. They are paired in groups of two each. One pair takes two-thirds the time needed by the second pair to complete the work. Which is the first pair?
  2. A.
    A and B
    B.
    A and C
    C.
    B and C
    D.
    A and D

    View Answer

    Workspace

    Answer : Option D

    Explanation :



Be The First To Comment