  1. Which of the following systems implementation approaches should be used if you want to run the old system and the new system at the same time for a specified period?

  2. A.
    direct
    B.
    pilot
    C.
    parallel
    D.
    phased
    E.
    None of the above

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    No answer description available for this question.