  1. To run the old system and the new system at the same time for a specified period, the system implementation approach used is

  2. A.
    pilot
    B.
    phased
    C.
    parallel
    D.
    direct
    E.
    None of the above

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    No answer description available for this question.