  1. The flownet of activities of a project is shown in the given figure. The duration of the activities are written along the arrows. The critical path of the activities is along

  2. A.
    1-2-4-5-7-8
    B.
    1-2-3-5-7-8
    C.
    1-2-3-6-7-8
    D.
    1-2-4-5-3-6-7-8

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    No answer description available for this question. Let us discuss.