Home / Civil Engineering / UPSC Civil Service Exam Questions :: Discussion

Discussion :: UPSC Civil Service Exam Questions

  1. What is the significant purpose of monitoring a project through its implementation phase ?

  2. A.
    To fix responsibility for delays
    B.
    To revalue the project with control over cost over-run
    C.
    To revalue the project with minimum time over-run
    D.
    To revalue the project with optimal time and cost over-run

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    No answer description available for this question. Let us discuss.


Be The First To Comment