  1. Consider the AoA network of a project shown in the given figure. (Activities are designated by alphabets and durations are shown around the stem of the arrow.) The critical path will be

  2. A.
    1-2-3-6-7-8
    B.
    1-2-3-5-7-8
    C.
    1-2-4-5-7-8
    D.
    1-2-4-6-7-8

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    No answer description available for this question. Let us discuss.