Home / Civil Engineering / Estimating and Costing :: Discussion

Discussion :: Estimating and Costing

  1. The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by prismoidal formula, is

  2. A.

    3250 m3

    B.

    3225 m3

    C.

    3275 m3

    D.

    3300 m3

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    No answer description available for this question.


Be The First To Comment