The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is
1.00 m3
1.25 m3
1.50 m3
1.75 m3
View Answer
Workspace
Share
Copy Text
Copy URL
Answer : Option B
Explanation :
No answer description available for this question.