Home / Civil Engineering / Estimating and Costing :: Discussion

Discussion :: Estimating and Costing

  1. Pick up the correct statement regarding the centre line method of estimating a building

  2. A.

    Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item

    B.

    The centre line is worked out separately for different sections of walls of a building

    C.

    The centre line length is reduced by half the layer of main wall joining the partition wall

    D.

    All the above.

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    No answer description available for this question.