  1. For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is

  2. A.

    0.90 m3

    B.

    0.94 m3

    C.
    0.98 m3
    D.
    1.00 m3

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    No answer description available for this question.